Thanks to Geoff Lilleker for help with some of this information. |
I won't be going into a lot of detail in this section, the intention is to give a general overview of the whole manufacturing process, so here goes : - |
Just as BAYKO retailers had two profit streams, selling both BAYKO Sets and spare parts, the manufacturing process had two operational streams to support them. |
. |
Process |
BAYKO Sets |
BAYKO Spare Parts |
Production |
This portion of the overall manufacturing process was common to both streams - not surprisingly, as the product was the same! |
|
Sub-Assembly |
The Brick Patterns were pre-assembled for inclusion in sets, likewise the boxes included in sets #3X and #4, accessory boxes [Rods, etc.] and Floor packs. |
BAYKO Spare Parts were packed in cardboard boxes or tubes, [or in plastic bags in the MECCANO era]. These were then used either for direct shipment... |
Final Packing |
The BAYKO Sets and Conversion Sets were assembled from the above stocks. |
...or to be packed into full or half Retail Display Cabinets. |
. |
||
Just for completeness, there was a third stream of more conventional order picking, for orders such as Bases, the various roofs, longer Rods [which would have been made-to-order], etc., which would then have been individually packaged as necessary. |
||
If you want to be really pedantic, I suppose you could also include the packing necessary to support the limited amount of direct supply to the public, particularly for those far flung parts of the globe!!! |
||
. |
||
► Production |
||
This section involved four separate manufacturing streams : - |
||
1 ► Plastic Parts |
While Plimpton were operating out of the Gibraltar Row site, they had six compression presses, each operated manually using a long lever to close the press. |
|
Parts were moulded from pre-measured quantities of powder using heat and pressure. |
||
Larger parts such as Bases, Roofs, early Roof Ends and Spans needed ejection pins to remove them from the mould and the marks of these [right] are easily seen on the finished parts. |
||
Moulds were cleaned, between pressings, using compressed air - though the occasional speckled brick suggests this, or the powder mixing, wasn't perfect. |
||
2 ► Rods |
All BAKYO Rods were simply cropped to the required length from longer lengths of wire which were, I understand, bought in - though Hollow Rods may have been different. |
|
A word of praise here... |
||
...for both Plimpton and MECCANO... |
||
...the standard of the cropped Rod ends was consistently very high, which had important safety considerations - no sharp edges. |
||
3 ► Ties & Links |
The basic outlines of these Cinderella parts were first produced using simple fly presses. |
|
Base Links were then drilled and tapped to create the holes and thread to accommodate the Screws. |
||
Tie-Bars were then, I believe, drilled with multi-headed drills. |
||
4 ► Floors |
Paxolin Floors were slightly different. |
|
They were bought in from outside suppliers, almost certainly already cut to size. The matrix of holes was then drilled, in house, also with multi-headed drills. |
||
. |
||
► Sub-Assembly |
||
This section involved three separate operational streams, the first two supporting the BAYKO set packing operation and the third, the spare parts operation : - |
||
1 ► Brick Patterns |
This was a reasonably skilled, somewhat labour-intensive process, almost certainly carried out by women. |
|
The primary objective here - apart from the logistics of creating stock items ready for the subsequent BAYKO set packing operation - was to 'stylishly' show off the colourful BAYKO parts to their best advantage in those sets. |
||
2 ► Boxed Parts |
► Boxes [or Bags] of Rods, Tie-Bars, Base Links, Screws, etc. ► Envelopes of Floors. ► Various cards of Arches bricks, Canopies, Doors and windows. ► One or more trays of bay window parts. ► Trays of other assorted parts. ► A number of boxes and trays of extra parts for sets #3X and #4. |
|
Throughout both the Plimpton and MECCANO eras, creating these sub--assemblies would have been an entirely manual task, almost certainly performed almost entirely by women. |
||
These sub-assemblies would all have been managed internally as standard stock control items, which would have been got ready, in advance, ready for the final BAYKO set packing operation. |
||
3 ► Spare Parts |
This would have been a similar, though much simpler, process [there was only one type of part per box in this case] to that described in section (2) above... |
|
...though we know limited mechanisation was introduced during the MECCANO era. |
||
. |
||
► Packing |
||
This section involved three separate streams : - |
||
1 ► BAYKO Sets |
This would have been an entirely manual [more likely womanual!] operation, with the set boxes being manufactured elsewhere. |
|
Remember, virtually everything, except Bases and Roofs, were in pre-packed sub-assemblies. |
||
N.B. - at its peak, BAYKO sold over 150,000 sets a year - so this was done on a significant scale. |
||
2 ► Retail Cabinets |
Once again, the final packing stage of the Retail Display Cabinets would have been an entirely (wo)manual operation. |
|
| I understand this operation primarily consisted of slotting pre-packed Spare Parts boxes, from stock, into the right sections of the Retail Display Cabinet. |
||
For their protection in transit, the Bases were usually, if not always, separated by rectangular pieces of corrugated cardboard... |
||
| ...the various BAYKO Roofs might well have been afforded the same protection. |
||
| 3 ► Individual Orders | This is probably the most traditional, and hence most familiar form of packing operation. |
|
Individual items, usually in standard order quantities or course, as well as pre-packed sub assemblies would be picked from stock by an individual and then wrapped, packed and labelled ready for dispatch. |
||
Very little direct evidence of this operation remains, though the wrapped packs of 12 x Flat Roofs, 6 x Large Roofs and 12 x White Domes shown in the slide show [right] give us a small insight. |
||
. |
||
Well, that's all there was to it... |
||
...unless you count the necessary warehousing and despatch operation. |
||
. |
||
There are quite a few gaps in our knowledge which I've tried to fill in with common sense, but if you've got any better ideas, then I'd love to hear from you... |
||
. |
||
Below here are links to related info : - |
||
|
. |
Click on any of the links below for related information.
|
||
. |
||
. |
||
. |
||
. |
||
. |
||
Latest update -
December 10, 2009
|
||